Audit Summary: Budget vs. Actual Spending
A
Created October 23, 2025About this video
Check out this video I made with revid.ai
Try the Text to Brainrot Video Generator
Create your own version in minutes
Video Transcript
Full text from the video
0:00
I've created the audit comparing your estimate to actual spending. Here are the main
0:00
takeaways: Good news: Your core project only went about 0.8% over the original
0:00
estimate (about 26,000 GYD), which is excellent control. Labour stayed exactly
0:00
on budget at 1,500,000 GYD. Areas of concern: Transportation was your biggest overage
0:00
- you spent 129,000 GYD versus the estimated 60,000 GYD (more than double) Sand went over by
0:00
98,000 GYD (you needed significantly more loads than estimated) Wood/Shores cost
0:00
38,500 GYD more than expected